Atlantic Coast Pipeline Canceled

Duke Energy and Dominion Energy said that lawsuits, mainly from environmentalists groups aimed at blocking the project — many of which were represented by Appalachian Mountain Advocates — had increased costs to as much as $8 billion from about $4.5 billion to $5 billion when it was first announced in 2014. We are so proud to be part of the coalition of citizens, communities, and organizations that worked together end this destructive and unnecessary pipeline.

Here is a sample of the press response:

New York Times –  Atlantic Coast Pipeline Canceled as Delays and Costs Mount

CNN – Energy companies cancel construction of Atlantic Coast Pipeline

Richmond Times Dispatch – Dominion cancels Atlantic Coast Pipeline, sells natural gas transmission business

Wall Street Journal – Companies Cancel Atlantic Coast Pipeline After Years of Delays